Monday, May 18, 2009

How Firm A Foundation... PR #26

May 18, 2009...Bright and early (it was so chilly!) Monday morning our excavator and footings contractor were on site to begin the actual construction process! We arrived around 7:30 A.M. to find them measuring and setting pins. It wasn't long until the digging began. Here's the first scoop of dirt being removed for the frost footers:

The back of the house will be set into the hill, with the ground floor walls in that area being poured concrete. Because the walls will be backfilled almost up to the second floor, frost footers weren't needed in that area. These "Form-A-Drain" footer forms are set on top of the ground and will remain in place after being filled with concrete, and will channel any water away from the foundation:

The "Form-A-Drain" being assembled and set into place:

Shameless plug for our excavator:

Shameless plug for the footings contractor (you wouldn't have believed how scrupulously clean this truck was):

OK...I DID take pictures of the Amish footings contractor. I wasn't trying to be disrespectful to his beliefs, just wanted to capture the moment. He worked steadily and swiftly...assembling the forms himself. He had an "English" co-worker who drove the truck and was assisting our excavator during the digging:

Trying to hold the camera level, this is looking from the house towards the driveway...you can see the well cap in the foreground:

Looking across the homesite:

View from the south side of the house, excavator continuing to dig for the frost footers:

Assembling the (non-frost) footer forms:

Our front door will be approximately where the bucket of the backhoe is digging (but on the second floor):

"Form-A-Drain" footer forms almost complete:

Handsome onlookers...can you tell they're freezing? It was a chilly morning.

View to the west, approximately:

Looking back towards homesite...this is what it looked like when we headed for home, around 9:30 A.M. You can see the footer forms on the ground towards the back and the ditches dug for the frost footers in the foreground:

We arrived back on site just before 12:30 P.M. You can see the small square forms in place in the center. Metal posts will be set on these pads to support the second floor:

Here they've used rocks to elevate the forms to the right height, and fill in gaps to contain the concrete:

Concrete truck arrived around 12:30 P.M. The truck driver spent a few minutes in discussion with the Amish contractor:

Moving into position to begin the pour:

Pouring and working with concrete really is hard work. As the concrete flows into the forms, it must be worked a bit to fill the space...

tamped down to remove air bubbles...and smoothed and leveled:

Work continued around the south side...one man operating the concrete truck, two men working, tamping, and smoothing the concrete:

After the concrete was smoothed, they came back with a wider, long-handled tool and smoothed it again:

Pouring on the north side:

The truck driver maneuvered his rig with skill...but he was close to the "edge" a few times:

Our children perched above the activity...taking it all in...anxious to see their new home become a reality:

Filling the small forms that will support the support posts for the second floor:

Smoothing, again:

And, about an hour later...the foundation and footers COMPLETE! The kids wanted to write in the hardening concrete in the worst way...but the workers were still on site and I didn't know if we should...besides, all this will be covered up. But, garage floor...look out! We'll be leaving our mark on you, for sure!

This was a busy morning...we had to arrange for the building inspector to be on site after the forms were in place, but before the concrete was poured. He arrived sometime during the three hours we were gone, and signed off on the footers and forms, so the concrete work proceeded as scheduled. One inspection down...only 18 more to go!

The footings contractor will return May 26th to set up the forms for the first floor walls, and I believe the framing will begin the following week. The second week of June should see us on site installing the under-slab plumbing and PEX tubing for the under-slab heating...after that...electrical? We'll see...

Stay tuned,
Kris

No comments: